Sunday, January 31, 2010

Bathroom Project Week 5

Week 5 was filled with pipes, paper and plaster.

It started out with the tub drain. With the tub in place and the PVC pipes already dry-fit, they can now be glued together. A little sandpaper, some purple primer, and a thin layer of cement is all it takes to join the pipes.
And that stuff is permanent - I accidentally spilled some on the dryer and now we have a purple polka-dot dryer. Sorry Cendy.
Griffey interrupts progress.
Shiny new white PVC drain is finished!
The next task is to re-locate the copper water supply pipes for the same reason we relocated the PVC drain - to raise them above the basement bathroom ceiling. We had to turn off the water to the whole house for this task.

Here you can see the new pipes running two new holes drilled into the floor beam. You can see the old clips underneath (and also where I cut them beyond the floor beam.)
A couple of 90 degree bends will re-connect the relocated pipe. First I needed to trim the pipe to allow room for the elbows. I can do it with my eyes closed!
Here's the access panel behind the tub. The old water supply pipes have been cut and the old shutoff valves were removed. They'll be replaced with valves that actually work.
Thanks to the Sharkbite connectors by the Cash Acme company, the pipes came together quickly. No solder or torch needed - just some elbow grease to put them into place.

Things got a little wet with the first test, but after re-tightening some screw fittings everything is dry and functional.
The next day we tested the tub drain and all connections checked out A-OK.
Behind this wall is our hall closet. To give our bathroom more storage, we decided to open this up to give access from the bathroom.
Here it is opened up and ready for drywall around it. We'll have to make a custom door to fit.
With Micah over to lend a hand, we put this large section of drywall in place. There are openings for the vanity light, medicine cabinet and GFCI receptacle.
Micah staples tar paper around the tub surround. This provides a layer of moisture protection behind the cement backerboard.
With tar paper finished, Micah looks on as I screw the first cement backerboard in place.
Here's the finished backboard in place. Next week we'll have the rest of it up.
A couple more pieces of drywall are put in place on this wall. There was a slight miscalculation with the piece at the bottom of the wall. We'll fix that next time.

Sunday, January 24, 2010

Bathroom Project Week 4

So we've been working on the bathroom for 4 weeks now. I've started putting some time in during the week to catch up with the goal of finishing by the Super Bowl (Feb 7).

We had our electrical inspection, and for the most part we "passed". However, there was one notable mistake that I had to fix.

By taking the old bathroom electrical wiring off the old circuit, I had spliced the rest of the circuit (hallway light, adjacent room receptacles, etc) and put it in its own box below the new dual switch box seen here.
The idea was to just cover this junction box and 'bury' it behind the drywall, but apparently that's an no-no. He suggested putting a splice in the new switch box, but after running the numbers I found that I needed a slightly larger box to accommodate all the wires. I also had to cut out half a stud (non-load bearing) to access the switch for the other room so I could re-wire it. The old wire wasn't long enough to reach the new box, so I went ahead and replaced the wiring for that switch and it's receptacle.

Here's the splice in the new box. The new switches were taken out to install the new box.
With the electrical taken done, the next step is drywall. Here's the ceiling above the shower with a new recessed light. The trick for tracing the circular cut-out is to put some lipstick on the edge of the can and press up your drywall panel against the can so that it "kisses" the panel with a circle. Next some construction adhesive and drywall screws secure it into place.
One panel up, two to go! It's green which means it's moisture resistant.
Two down!
And done!
Next up, tub...

It's a fiberglass tub, so the instructions call for it to rest on foundation of plaster to help support the bottom. I've read that Sand Mix is also appropriate. It's a mixture of sand and Portland cement that's combined with water to create a concrete-like slab for the tub to rest on.


The tub to placed on the mound of wet concrete. Next we stood on the tub to smoosh down the concrete so that it bears nicely on the bottom.

Since the alcove isn't perfectly square, so we use some shims to nail the tub to the studs.
This wall next to the tub will have a niche for shampoo bottles, soap, etc. That's what we have framed out in this picture.
And since the alcove isn't square, new studs are nailed to the old ones so we'll have walls that are parallel to the tub flanges.
The new medicine cabinet will be recessed between two wall studs. Here we find that the medicine cabinet is 1/4" too wide so I had to cut one of the studs to create a larger opening.
Luckily I didn't damage the drywall for the adjacent room when removing the old stud. A 1/4" is all we needed.

Monday, January 18, 2010

Bathroom Project Days 6-8

Martin Luther King weekend was spent carrying out our electrical plan.

First this old switch/receptacle is disconnected and the circuit is re-wired to skip the bathroom.
Power from the panel is coming in from the top left, and is simply spliced with the branch going to the adjacent room (out the bottom of the box) and the hallway light branch (out the upper right). This junction box will be covered up and live behind the drywall.

Here I cut the hole for the bathroom fan vent.
Looks good!
A little black roof cement and some roofing nails finish the job. It rained the next day, and we were able to see that it stayed dry inside.
Here's the empty fan box mounted to the ceiling. A flexible duct connects the box to the roof vent. The fan assembly snaps inside the box.
Next the can light over the shower is installed. This recessed light is "IC" which means "insulation contact" - it's designed to not start a fire if it's covered with ceiling insulation.
Now the vanity light is mounted. This is connected to the shower light in series so they both turn on with the flip of a switch. (It'll look nicer with the pretty bulb globes attached)
The switch on the right is for the lights, an the one of the left is for the fan. The black wires are existing wiring from the panel and the hallway light.Next the GFCI receptable is installed about 1' from the sink. It's rated for 20A, so bring on those power hungry hair dryers!
Now is the part that made me the most nervous - working inside the panel. For safety, we turned the entire house off. However, the power feed coming from outside is still hot. After some research, we learned the proper precautions and everything went smoothly, although Cendy secretly had 911 on speed dial in case something happened.

The bottom right breaker is a special 15A GFCI circuit breaker. It is required by code to have the shower light GFCI protected. This is one way to accomplish that, and we're protecting the fan and vanity light while we're at it. About 3 slots up from the new breaker was an unused existing 20A circuit breaker that I used for the new GFCI receptacle in the bathroom.

We were still nervous as we prepared to test the fixtures...
IT'S ALIVE!!!

And the receptacle works too! That orange contraption tests the wiring in receptacles.

The last accomplishment for the weekend was insulating the fan duct. This prevents condensation around the duct when warm bathroom air runs through a cold attic.

Sunday, January 17, 2010

Bathroom Project Day 5

Last weekend wasn't as productive as we planned. Electrical work has always made me nervous, but that's really from lack of knowledge. They say if you're exposing old wiring, it's best to replace it while you're at it. So, Saturday was spent planning the electrical circuits and reading up on the how to safely tackle this portion of the project.

There were three circuits to tackle.

1. Remove current bathroom electrical lines from the existing circuit.
2. Install new 20A circuit for bathroom GFCI (ground fault circuit interrupter) receptacle.
3. Install new 15A circuit for bathroom fan and lights.

First was the existing bathroom circuit, which also had the hallway light and adjacent room receptacles on it. The bathroom is the L-shaped room in the middle of the page. Power goes from the circuit panel to a switch/recepticle in the bathroom, then to the hallway light & receptacle and then to the adjacent room recepticles. Also found that this circuit has the basement laundry room light on it. Random.


To remove the old bathroom wiring from the circuit, I removed the old receptacle box and switch and light fixture wire. Then, I installed a new junction box to connect power from the panel to the hall light and adjacent room receptacles.
Second phase is new 15A wiring for a new fan, light fixture over the sink and can light over the shower. The lights are on one switch, and the fan is on another.
The third circuit is easy - a 20A GFCI receptacle all by itself!
Last Sunday we had to put our plumbers hats on. We spent all day wrestling drain snakes to battle a clog in our main house drain. After coming -this- close to giving up and calling a pro, we finally figured it out, cleared the clog and saved ourselves a few hundred bucks.

Sunday, January 3, 2010

Bathroom Project Days 3 - 4

Now that demolition is finished, the work gets a little more challenging. It seemed like most of my time was spent scratching my head.

Here's the hole in the floor to remove the water damaged planks. We put the new tub in place to check the fit, and it's partially covering the hole.

The new tub fits fairly well. It's about an inch too wide and an inch too short (length-wise), but we'll make it fit. We'll also dry-fit the new tub drain while it is in place.

Here's how the old bath drain was routed (1 1/2" diameter white PVC pipe). As mentioned previously, this runs too low and will hang below the ceiling of our future 3rd bathroom in the basement.
So I set the P-trap to take a 90 degree turn to go through a floor stringer, and turn back and head towards to main drain.
I was a little nervous drilling a 2" diameter hole in the 2"x8" floor stringers, especially since this was near midspan of the beam. Originally I was going to drill more to the right in this picture, but will all the knots at the top and bottom of the section (and a few cracks nearby), I decided to place the shown as shown in this picture. We're looking up through the hole in the floor and can see the tub.

We removed the tub to repair the floor. The opening to the right of the repair is for the tub drain.
I nailed some 2x4's to the wall to make up the distance for the shorter tub. Also shown is the new ledger board that the tub will rest upon.